What was the starting point?
The company's shift-based field teams, security staff and headquarters employees worked under different time and attendance and approval rules. The goal was for payroll, leave and overtime processes to run in a single system, consistent with financial postings, and for employees to be able to handle their own transactions through a portal.
How did the project progress?
The work began with analysis and conceptual design; customization, development, integration and testing steps were then carried out in two phases. Personnel master data was migrated, infotypes, the payroll schema and wage types were set up, and go-live was carried out according to a cutover plan.
In time management, shift definitions, time and attendance transfer, special leave types such as half-day excused leave, and overtime approval were set up; a substitute structure that takes over approvals when a manager is absent was added. In payroll, severance and notice pay calculations, garnishment and alimony deductions, net-to-gross calculation, annual leave advances and retroactive payroll were addressed.
What was done for the portal and integrations?
In the employee and manager portal, leave requests and approvals, manager-initiated leave requests on behalf of employees, the personnel card, leave reports and the organizational chart were rolled out. Forms and workflows were developed for organizational assignments.
The integration between payroll and finance was rebuilt according to the sector-specific chart of accounts. Employees' organizational information and the data required for emergency planning were transferred to external systems through the integration layer; the workplace physician process was also brought into scope.
What happened after the project?
After go-live, IKSAP continued support for period payrolls, payroll summary checks, time and attendance errors and portal requests. Personnel cost planning work, documentation of the developed programs and user training were also completed during this period.
Assessment
In field-heavy energy companies, designing time and attendance and approval rules at the start of the project together with substitution and shift scenarios significantly reduces the correction workload after go-live. Treating finance integration as part of the HR project also speeds up payroll closing.
Frequently Asked Questions
What steps did the project follow?
Analysis and conceptual design, customization, development, integration, testing and go-live; the scope was split into two phases.
Which transactions were included in the employee portal?
Leave requests and approvals, manager-initiated leave requests on behalf of employees, the personnel card, leave reports and the organizational chart.
Which integrations were built?
An integration between payroll and finance aligned with the sector-specific chart of accounts, and integration interfaces that transfer personnel data to external systems.